Commissioner SMC reviews AMRUT works


Srinagar: Commissioner Srinagar Municipal Corporation (SMC), Gazenfar Ali, today reviewed progress of various projects under AMRUT scheme.

The status of all the works under AMRUT that included Sewerage and Septage, Drainage sector, Rejuvenation of Brari Nambal, Urban Transport sector, Green Space sector, Water Works sector and other issues were discussed at length.

The Commissioner was informed that out of the total number of thirty projects that have been identified under AMRUT, 16 stand completed and 7 projects have 80 percent physical progress and four shall be completed by the month of September 2020.

Regarding STP’s   he was informed that both STP’s one at Achan and the other at Aaluchibagh are completed and fully functional.

While reviewing the status of walkways the meeting was informed that walkways at Peerbagh, Tengpora, Rambagh and Shireen bagh have been completed and an idle parking in Pantha Chowk is also completed.

Commissioner SMC directed all the concerned wings to expedite the progress of remaining works and complete them within the stipulated time.

The meeting was attended by Joint Commissioner (works), SE Drainage, ADP Planning, all Executive Engineers, representatives of SDA, LAWDA, Floriculture, UEED and others.