Power shutdown


 
Srinagar: According to the Power Controller, Kashmir Province, in order to carry out urgent repairs and erection of ST Poles, shut down of 33 kV line of STD Bijbehara shall be observed as per programme below.

During the shutdown, the power supply to areas fed from Receiving Stations Kokernag and Dandipora will remain affected on 24 June from 9 am to 5 pm.

Similarly to carry out replacement of C&R Panel at 40 MVA, 220/132 kV Grid Station Pampore, shutdown of transformer bank 220/132 kV Grid Station Pampore shall be observed as under.

During the shutdown, the power supply via transmission line 220 D/C   Wagoora-Pampore Circuit- II will remain affected on 26 June from 9 am to 5 pm.