Srinagar: According to
the Power Controller, Kashmir Province, to execute installation of 630 kVA
transformer at Iqbalabad Bemina near Degree College Bund, the shutdown of
Bemina Exhibition Line is being observed.
During the shutdown, the power
supply to the areas fed from 33 kV Bemina Exhibition line shall remain affected
on July 19 from 11 am to 12 noon.
Similarly, as per separate
statements the Superintending Engineer, O&M Circle II, KPDCL Srinagar, to execute
the ongoing IPDS Scheme, shutdown of 11 kV feeder No’s F3 and F1 of Bemina Ist
Receiving Station and Feeder F4 of Karan Nagar Receiving Station shall be
observed.
During the shutdown, the power
supply to the feeder no’s F1 and F3 fed from Bemina Ist Receiving Station shall
remain affected on July, 21 and feeder no. F1 also fed from Bemina Ist
Receiving Station shall remain affected on July, 22 from 10 am to 4 pm
respectively.
The power supply to the feeder
no. F4 fed from Karan Nagar Receiving Station shall remain affected on July, 22
and 23 from 10 am to 4 pm.
In order to replace old
deteriorated poles and conductors by new ones from Batamaloo Adda to Hamdard
Hospital, the shutdown of feeder no. 5 of the Receiving Station Exhibition
shall be observed on July, 20 and 21 from 10:30 am to 5 pm.
Similarly to carry out HT/LT
pole erection at Tengpora and Maharajpora, the shutdown of 11kV Feeder No. 2 of
Receiving Station Danderkhah shall be observed on July, 20 and 22 from 11 am to 2 pm and on July, 25 from 11
am to 3 pm.