DC Jammu
inspects progress at several construction sites
|
Jammu: The work on Jammu–Akhnoor Four lane project
has gained substantial momentum with the execution of 31 percent work on
Package II of the project which starts from 800 meters and ends at 6 km (from
canal head to Ganesh Vihar). It includes construction of 4.6 km long
flyover. The flyover will have 126
foundations out of which 93 have been completed. Also the work on package III
has gained pace which starts from Ganesh Vihar to Khati Chowk (km 06 to km 26.350).
The Deputy Commissioner, Jammu
Ms. Sushma Chauhan, IAS visited various construction sites and inspected the
pace of progress on the project. ACR Jammu, Vijay Sharma, SDM Jammu North, Sh.
Pawan Kotwal besides officers from PHE, PDD, NHIDC and other concerned
departments also accompanied the Deputy Commissioner.
The senior functionaries of
executing agency (NHIDCL Engineers) briefed the Deputy Commissioner Jammu about
the work done so far.
The Deputy Commissioner was
further informed by the Site Engineer that clearance of structures is complete
with all the 580 structures having been cleared in last one year. It was
further told that over 90% land/structure compensation has been disbursed to
the rightful claimants.
Giving further details, the DC
was told that a total 11.618 km hindrance free stretch has been completed in
the last one year.
The Shifting of PDD poles and
the infrastructure of PHE department coming in the alignment of the project
shall be completed in a scheduled manner. The instructions have been issued by
Deputy Commissioner to the concerned officers to adhere with the instructions
and get the work completed in a time bound manner. The on spot directions have
been issued to General Manager NHIDCL to improve the condition of in use
service lanes. The patch work shall be completed in a week’s time so that the
general public may not suffer due to the poor condition of the road.